Projects and Programs Done So Far in Enugu North
# | Project | Completion Status |
---|---|---|
1 | Construction and asphalting of the 2.2km European Quarters Road, Hilltop | 45% completion |
2 | Construction and asphalting of 400m Owa Street, Coal Camp | 80% completion |
3 | Reconstruction and asphalting of Ukwa Street, Off Presidential Road | 50% completion |
4 | Reconstruction and asphalting of Chris-Chemist to Ogbete Main Market Road, including removal of roundabout | 100% completion |
5 | Reconstruction and beautification of Chris-Chemist to Holy Ghost Median | Ongoing |
6 | Installation of solar-powered CCTV along Chris-Chemist, Holy-Ghost, and Ogbete axis | Completed |
7 | Installation of wire mesh along Chris-Chemist to Holy Ghost axis to aid decongestion | 50% completion |
8 | Establishment of a mobile court for offenders to reduce traffic gridlock | 100% completion |
9 | Procurement of 500 solar street lights for deployment across various wards | – |
10 | Completion and re-equipping of the Idume Community Health Centre | 40% completion |
11 | Deployment of solar street lights across the council secretariat | Completed |
12 | Renovation of Enugu North LGA Multi-purpose city hall | Ongoing |
13 | Re-organization and formalization of the Neighborhood Watch Program | Completed |
14 | Equipping of offices at the newly reconstructed Administrative Block | Completed |
15 | Deployment of an e-collection platform to optimize LGA revenue sources | – |
16 | Development of a fully integrated LGA website for e-governance transition | Ongoing |
17 | Recovery of all LGA construction equipment | – |